Granny Flat Approval Process Sydney: CDC vs DA Explained
Confused about granny flat approvals in Sydney? Learn the difference between Complying Development Certificates (CDC) and Development Applications (DA), and discover which approval pathway suits your project best.

Serenity Building Group
10 min read

Key Takeaways
- Complying Development Certificates (CDC) offer faster approval (typically 20 business days) for granny flats meeting specific size and setback requirements
- CDC granny flats must be under 60 square metres and meet strict setback requirements of at least 3 metres from boundaries
- Development Applications (DA) are required for granny flats exceeding CDC limits or on challenging sites, with approval times of 8-12 weeks
- CDC applications cost significantly less than DA applications, typically $2,000-$4,000 versus $5,000-$10,000+ for DAs
- Heritage areas, bushfire zones, and flood-affected properties often require DA approval regardless of granny flat size
- Professional design and certification are essential for both pathways to ensure compliance with Building Code of Australia
- Construction Certificate (CC) approval is required after DA/CDC approval before building work can commence
Understanding Granny Flat Approvals in Sydney
Granny flats have become increasingly popular in Sydney as a solution for housing affordability, multi-generational living, and rental income opportunities. However, navigating the approval process can be confusing, with different pathways offering varying benefits and constraints.
At Serenity Building Group, we specialise in granny flat approvals and construction throughout Sydney. This comprehensive guide explains the key differences between Complying Development Certificates (CDC) and Development Applications (DA), helping you choose the most appropriate approval pathway for your project.
Overview of Approval Pathways
In NSW, granny flats can be approved through two main pathways, each with distinct advantages and limitations depending on your specific circumstances and project requirements.
Complying Development Certificate (CDC)
CDCs provide a faster, more streamlined approval process for granny flats that meet specific predetermined criteria:
- Faster processing: Typically 20 business days from submission
- Lower cost: Generally $2,000-$4,000 in total fees
- Certainty: Must be approved if compliant with standards
- Limited assessment: No neighbour notification or council discretion
Development Application (DA)
DAs provide more flexibility but involve longer processing times and higher costs:
- Greater flexibility: Can exceed CDC size and setback limits
- Longer processing: 8-12 weeks assessment period
- Higher cost: $5,000-$10,000+ including professional fees
- Merit assessment: Council has discretion to refuse applications
CDC Requirements and Limitations
Complying Development offers fast approval but requires strict compliance with predetermined standards. Understanding these requirements helps determine if CDC is suitable for your project.
Size and Design Limitations
CDC granny flats must comply with specific size constraints:
Requirement | CDC Limit | DA Alternative |
---|---|---|
Maximum floor area | 60 square metres | No limit (subject to FSR) |
Maximum height | 8.5 metres | Varies by zone |
Side setback | Minimum 0.9m | May be reduced |
Rear setback | Minimum 3m | May be reduced |
Site and Zoning Requirements
Your property must meet specific criteria for CDC approval:
- Minimum lot size: 450 square metres (varies by council)
- Zoning compliance: Residential zones only (R1, R2, R3, R4)
- Heritage restrictions: Generally not available in heritage conservation areas
- Bushfire areas: Special provisions apply in bushfire-prone land
- Flood zones: Additional requirements for flood-affected properties
Design and Construction Standards
CDC granny flats must meet specific design criteria:
- Single storey only: Multi-storey granny flats require DA approval
- Detached or attached: Must be separate dwelling or secondary dwelling attached to main house
- Parking provision: One covered parking space required
- Privacy screens: Windows facing neighbours may require screening
- Waste management: Adequate bin storage and collection access
Development Application Pathway
When your granny flat project exceeds CDC limitations or site constraints prevent CDC approval, the DA pathway provides greater flexibility at the cost of longer approval times and higher fees.
When DA is Required
Several scenarios mandate DA approval instead of CDC:
- Size exceedance: Granny flats larger than 60 square metres
- Setback variations: Reduced setbacks from boundaries
- Heritage areas: Properties in heritage conservation areas
- Multi-storey design: Two-storey granny flats
- Challenging sites: Steep slopes, flood zones, or contaminated land
- Multiple dwellings: More than one secondary dwelling
DA Pathway Advantages
Development Applications offer several benefits over CDC:
- Size flexibility: No 60 square metre restriction
- Design innovation: More creative architectural solutions
- Site optimisation: Better use of challenging sites
- Multi-storey options: Two-storey designs for better space utilisation
- Setback variations: Reduced setbacks where appropriate
DA Assessment Process
The DA process involves comprehensive assessment by council:
- Application lodgement: Detailed plans and supporting reports
- Public exhibition: 14-day neighbour notification period
- Assessment: Council evaluation against planning controls
- Determination: Approval, refusal, or request for modifications
Cost Comparison: CDC vs DA
Understanding the total costs involved helps you budget appropriately for your granny flat approval and construction.
CDC Total Costs
CDC applications generally involve lower total costs:
- Application fees: $1,200-$2,500 depending on council
- Design documentation: $2,000-$4,000 for plans and specifications
- Engineering reports: $1,500-$3,000 if required
- BASIX assessment: $300-$600 for energy efficiency compliance
- Total CDC costs: $5,000-$10,000
DA Total Costs
DA applications typically involve higher upfront costs:
- Council DA fees: $2,000-$5,000 depending on value and council
- Architectural plans: $3,000-$8,000 for detailed design
- Planning report: $1,500-$3,000 for planning assessment
- Engineering reports: $2,000-$5,000 for structural and services
- Specialist reports: $2,000-$8,000 (bushfire, heritage, etc.)
- Total DA costs: $10,000-$25,000+
Timeline Comparison
Processing times vary significantly between approval pathways, affecting your project planning and construction scheduling.
CDC Processing Timeline
CDC applications follow a streamlined timeline:
- Design and documentation: 2-4 weeks
- Application lodgement: 1 week for submission
- Council assessment: Maximum 20 business days
- Construction Certificate: Additional 2-3 weeks
- Total timeline: 8-12 weeks from start to construction
DA Processing Timeline
DA applications require longer processing periods:
- Design and documentation: 4-8 weeks
- Application lodgement: 1-2 weeks for submission
- Council assessment: 8-12 weeks (can be longer)
- Potential delays: Additional information requests, resubmissions
- Construction Certificate: Additional 3-4 weeks
- Total timeline: 16-24 weeks from start to construction
Construction Certificate Requirements
Both CDC and DA approvals require a Construction Certificate before building work can commence. This additional step ensures building compliance.
Required Documentation
Construction Certificate applications require detailed technical documentation:
- Detailed construction drawings: Comprehensive building plans
- Structural engineering: Foundation and frame design
- Services engineering: Electrical, plumbing, mechanical plans
- BASIX compliance: Energy and water efficiency measures
- Accessibility compliance: Where required under Building Code
CC Costs and Timeline
Construction Certificate processing adds time and cost:
- Application fees: $800-$2,000 depending on project value
- Professional documentation: $2,000-$5,000
- Processing time: 2-4 weeks after submission
- Inspection fees: $200-$500 per inspection during construction
Choosing the Right Approval Pathway
The choice between CDC and DA depends on your specific project requirements, site constraints, and priorities regarding cost, timeline, and design flexibility.
When CDC is Most Suitable
Consider CDC approval when:
- Standard requirements: 60 square metres or less is adequate
- Compliant sites: Standard residential blocks with adequate setbacks
- Time priority: Faster approval is more important than design flexibility
- Budget constraints: Lower approval costs are essential
- Simple design: Single-storey, straightforward granny flat
When DA is Necessary or Preferable
Consider DA approval when:
- Size requirements: Need more than 60 square metres
- Design complexity: Two-storey or architecturally distinctive design
- Site constraints: Challenging sites requiring reduced setbacks
- Heritage areas: Properties in heritage conservation areas
- Premium outcomes: Design quality more important than cost/time
Professional Assistance and Documentation
Both approval pathways require professional design and documentation to ensure compliance and approval success.
Design Professional Requirements
Qualified professionals ensure compliant and successful applications:
- Architect or designer: Planning-compliant design development
- Draftsperson: Technical drawing preparation
- Engineer: Structural and services design
- Planning consultant: DA pathway advice and submission
Builder Involvement
Experienced granny flat builders provide valuable input:
- Early consultation: Constructability and cost advice
- Design input: Practical construction considerations
- Approval support: Documentation and submission assistance
- Project continuity: Seamless transition from approval to construction
Making Your Granny Flat Approval Decision
Understanding the differences between CDC and DA pathways empowers you to make informed decisions about your granny flat project. While CDC offers speed and cost advantages, DA provides flexibility for more complex or larger projects.
At Serenity Building Group, we guide you through the entire granny flat process, from initial feasibility assessment through approval to construction completion. Our experience with both pathways ensures your project follows the most appropriate approval route.

Serenity Building Group
Sydney's Premier Building & Construction Specialists
Serenity Building Group is a trusted building and construction company serving all areas of Sydney. With over 15 years of experience in all aspects of building work, our team delivers exceptional craftsmanship on every project. Our comprehensive approach, emergency response capabilities, and commitment to quality and excellence have made us trusted advisors to homeowners, property investors, strata managers and commercial property owners throughout Sydney.